To complete the final connections between the new Gibraltar Village water pipeline and the Happy Valley network (two more connections are required), temporary traffic management will be in place at the main Gibraltar Village entry road to complete the first.
Dates: Thursday 12/3/26 and Friday 13/3/26Time: 08:00 – 15:00 hrs
Affected Area: Gibraltar Village
The main entry road will remain open under traffic control, and short delays may occur.
Please note:
Only normal-sized vehicles will be able to pass; trucks and heavy vehicles will not be permitted.
Emergency access will be maintained via the Bondu area if required and with metal plates in case needed.
The Snake Path pedestrian route will be closed at both the Gibraltar and Happy Valley ends during these hours.
Temporary pedestrian routes will be available for Gibraltar access only.
No water supply interruption is expected. Normal access will resume once works are completed.
The Final water connection that will also conclude the project will be scheduled for 19/3/26 and will require the closure of Happy Valley tunnel to cross the road, follow up email to follow.